A recent judgment of the Supreme Court of India in T.D. Vivek Kumar & Anr. vs. Ranbir Chaudhary[1] deals with the right to specific performance of a contract which stipulates payment of double the amount given as an advance in case of its breach. In this case, the Court held that where an agreement of sale stipulates that in case the seller fails to execute the sale deed within the prescribed time, it shall be liable to pay double the earnest money, the specific performance of such an agreement cannot be granted. However, this view ignores earlier precedents of the Apex Court on this very issue as outlined below and hence warrants a re-examination of the law relating to the equitable right to specific performance.
Section 10 of the Specific Relief Act, 1963 (“the 1963 Act“) deals with cases in which specific performance of contract is enforceable. It provides that, except as otherwise provided, specific performance of a contract may, in the discretion of the court, be enforced when the act agreed to be done is such that compensation in money for its non-performance would not afford adequate relief. Explanation (i) to Section 10 provides that:
“Explanation. – Unless and until the contrary is proved, the court shall presume –
(1) A contract, otherwise proper to be specifically enforced, may be so enforced though a sum be named in it as the amount to be paid in case of its breach and the party in default is willing to pay the same, if the court, having regard to the terms of the contract and other attending circumstances, is satisfied that the sum was named only for the purpose of securing the performance of the contract and not for the purpose of giving to the party in default an option of paying money in lieu of specific performance.
Read More+
(2) When enforcing specific performance under this section, the court shall not also decree payment of the sum so named in the contract.”
“20. Liquidation of damages not a bar to specific performance. – A contract, otherwise proper to be specifically enforced, may be thus enforced, though a sum be named in it as the amount to be paid in case of its breach, and the party in default is willing to pay the same.”
The significant difference between the two provisions was explained by the Supreme Court in Kamal Kant Jain vs. Surinder Singh (Dead) through legal representatives[2]. A two-judge bench noted therein that the new section 23 “explicitly provided that the mere naming of a certain amount which may sound in damages is not good enough by itself to non-suit a person seeking specific performance unless it is clear on the facts that the said sum was named in lieu of specific performance”.
A good starting point for this analysis is a 1973 judgment of the Supreme Court in M.L. Devender Singh vs. Syed Khaja[3]. Here, an agreement for sale of a residential house provided that if the seller failed to comply with the terms thereof, he would be liable to refund the advance money plus a similar amount as damages to the purchaser. The Court noted that there was no stipulation in the agreement that the party in breach will have the option to either fulfil the contract to buy or sell or to pay the specified liquidated damages as an alternative to the performance of the contract.
The Court also examined the language of the new Section 23 and held that it contained a comprehensive statement of the principles on which, even before the Act of 1963, the presence of a term in a contract specifying a sum of money to be paid for a breach of the contract has to be construed. The Court further held that where payment is an alternative to carrying out the other terms of the contract, it would exclude, by the terms of the contract itself, specific performance of the contract to convey a property.
The Court relied on the following exposition of law in Sir Edward Fry’s “Treatise on the Specific Performance of Contracts” (Sixth Edn. at p. 65):
Where the stipulated payment comes under either of the two first-mentioned heads, the court will enforce the contracts, if in other respects it can and ought to be enforced, just in the same way as a contract not to do a particular act, with a penalty added to secure its performance or a sum named as liquidated damages, may be specifically enforced by means of an injunction against breaking it. On the other hand, where the contract comes under the third head, it is satisfied by the payment of the money, and there is no ground for the court to compel the specific performance of the other alternative of the contract.”
Observing that the equitable principles evolved by the Courts in England have been accorded statutory form in India, the Court held that the jurisdiction of the court to decree specific performance could not be curtailed or taken away by merely fixing a sum as liquidated damages. It was further held that a contractual stipulation of payment of money in case of a breach is nothing more than a piece of evidence (which is neither conclusive nor decisive) to be considered while considering grant of specific performance.
Around two and a half decades later, the Apex Court, in a discordant note, held in Dadarao vs. Ramrao[4] that since the agreement sought to be enforced therein itself provided the consequences if either the seller refused to sell or the buyer refused to buy, a sale deed could only be executed if both parties agreed to do so. In that case, the agreement provided that in addition to the earnest money of Rs 1000, a sum of Rs. 500 was to be given back to the buyer and that “no sale deed will be executed”.
This judgment was subsequently distinguished by the Supreme Court in P. D’Souza vs. Shondrilo Naidu[5] and P.S. Ranakrishna Reddy vs. M.K. Bhagyalakshmi[6]. In P. D’Souza (supra), the Court held:
“34. In Dadarao whereupon Mr. Bhat placed strong reliance, the binding decision of M.L. Devender Singh was not noticed. This Court furthermore failed to notice and consider the provisions of Section 23 of the Specific Relief Act, 1963. The said decision, thus, was rendered per incuriam.”
In 2010, a two-judge bench of the Supreme Court, in Man Kaur (Dead) by LRs vs. Hartar Singh Sangha[7], dealt with an agreement between the parties which provided that if the seller committed a default, he had to pay double the amount of the earnest money to the purchaser. The Court held that under Section 23, even where the agreement of sale contained only a provision for payment of damages or liquidated damages in case of breach and did not contain any provision for specific performance, the party in breach could not argue that the court cannot grant specific performance. However, where the provision naming an amount to be paid in case of breach is intended to give to the party in default an option to pay money in lieu of specific performance, then specific performance may not be permissible.
On facts, the Court ultimately found that since the agreement neither provided for or barred specific performance expressly, the purchaser will be entitled to seek specific performance subject to proof of breach by the defendant and his own readiness and willingness to perform the contract.
In Kamal Kant Jain (supra), the agreement to sell stated that if the seller backed out from the deal, he would refund the earnest money with an equal amount as penalty for non-fulfilment of the contract. The Court found that such a statement will not debar specific performance.
Unfortunately, the Court, while deciding T.D. Vivek Kumar (supra), neither deigned to examine the legal position in detail nor considered that the agreement, in that case, nowhere stated either that the purchaser will not be entitled to claim specific performance or that the monetary amount named therein was in lieu of specific performance. Hence, this view not only ignores the authoritative body of law rendered by coordinate benches in the past, but also begs the question whether the judgment is susceptible to being declared per incuriam in future, although that will offer little solace to the losing party therein.
It is desirable, nay imperative, that an authoritative bench of the Supreme Court puts this issue to rest.
Footnote
[1] 2023 SCC Online SC 526.
[2] (2019) 11 SCC 432.
[3] (1973) 2 SCC 515.
[4] (1999) 8 SCC 416.
[5] (2004) 6 SCC 649.
[6] (2007) 10 SCC 231.
[7] (2010) 10 SCC 512.
This article was originally published in Mondaq on 12 May 2023 Written by: Ajit Warrier, Partner. Click here for original article
Read Less-
Disclaimer
This is intended for general information purposes only. The views and opinions expressed in this article are those of the author/authors and does not necessarily reflect the views of the firm.
The Bar Council of India does not permit solicitation of work and advertising by legal practitioners and advocates. By accessing the Shardul Amarchand Mangaldas & Co. website (our website), the user acknowledges that:
Click here for important public notice from the Firm.