The phenomenal growth in renewable energy generation capacity has been one of the undisputed success stories for India. A combination of favourable policy initiatives, abundant solar and wind resources, the “green shift” in the availability of global finance, emergence of sophisticated domestic developers and a steep fall in module prices worldwide has resulted in the sector growing in leaps and bounds. At the end of Q-3, 2020, the large-scale solar project pipeline stands at 44.7 Gigawatt (GW) with another 34.6 GW pending auction (according to Mercom India Research’s Q3 2020 India Solar Market Update). To give some context, India had committed under the Paris Agreement of 2016 that 40% of its energy generation would be from renewable sources by 2030- in the end of 2020, this number already stands at 37% (including hydroelectric power).
Yet the sector has run into unexpected headwinds. Concern has been growing about a significant backlog of projects facing delays. There are a number of reasons for this: the impact of the COVID-19 pandemic; including on module supplies from China; fluctuations of global module prices; significant issues with respect to land acquisition and allotment to power plants; and environmental issues (including habitat protection for endangered bird species and protection of ancient forest groves) have all contributed.
Read More+
One of the most critical challenges, ironically, has emerged from one of the greatest successes-falling tariff prices. Solar tariffs have fallen by 50% in the last few years. An industry-stunning Rs 2.00 per unit bid held the lowest tariff record for less than a month, to be replaced by a Re 1.99 per unit bid. But this Icarus seems to have flown too close to the sun.
The trouble is that once solar tariffs are determined through a competitive bidding process, they are encapsulated in long term power purchase agreements (PPAs) and are not subject to further changes for the entire term of the PPA. But (usually) state owned distribution companies (DISCOMs), who are the ultimate purchasers of power see the tariffs fall every week or so, and therefore are disincentivized to tie themselves up to long term contracts at what they consider to be higher prices (It was a similar myopic pursuit of the lower tariff possible that led Andhra Pradesh to embark on the renegotiation misadventure with respect to executed contracts).
What this means is that there are now a significant number of projects which have successfully participated in bids, but for which long term PPAs have either not been executed, or not become effective.
To understand this problem in more detail, we need to briefly understand the mechanism of renewable power purchase in India:
The net result has been that for several hundreds of MW of projects for which Letters of Award (LOAs) have been awarded post completion of tenders and PPAs executed, either the PSA is not executed, or, even if the PSA has been executed, the capacity approval has been indefinitely delayed. It is estimated that this issue affects 6.5- 12 GW of projects. (The Central Electricity Authority in its August 2020 Report on the renewable sector notes that 39.4 GW of “pipeline” renewable projects are delayed, a significant number of which is for delays in execution or approval of PSAs).
Even the trading margin which SECI/ NTPC has been charging, has been the source of endless dispute, with DISCOMs often backtracking on accepting trading margins they had already consented to in the past, and then having the issue drag through the labyrinth of the CERC determination process.
The problem is that from a tendering law perspective, a LOA is not legally binding and therefore SECI has the ability to withdraw or terminate a tender process any time prior to the actual signing of the PPA. Further, the PPA also usually contains a clause that allows either SECI or the developer to terminate the PPA in case the relevant regulatory approval is not in place. Therefore, the developer has limited legal options in such a case. However even in such circumstances, there are instances of developers becoming exasperated with the delays and walking away from PPAs. For example, three developers, ACME Solar, Shapoorji Pallonji, and Azure Power projects terminated PPAs for around 1.4 GW of capacity citing regulatory delays.
Unfortunately DISCOMs typically lack the understanding of the complexity of risks that drive bid behaviour, nor have they bought into the idea of the requirement to develop the sector at multiple levels. For example, SECI has been active in seeking manufacturing linked solar auctions, where the discovered tariff would obviously be higher that standalone generation auctions. SECI’s solution has been to pool the different types of tariff together and provided a weighted average tariff to the DISCOMs. SECI has even proposed pooling power acquired through auctions over 6 months and bundling them but approval of this solution is pending with the CERC.
The only solution seems to be for SECI to approach the auction after receiving the necessary confirmation from DISCOM(s) with respect to acquisition of power. This however, has major disadvantages. The larger DISCOMs (such as Gujarat and Rajasthan) would benefit from low tariffs, whereas many of the other states (considered risky by developers) will struggle to find bidders or face disproportionately high tariffs.
Delays in execution or approval of the PSAs creates business uncertainty for the developer, who are suspended in limbo for months. As tariffs fall, the uncertainty becomes exacerbated. Lenders usually would not disburse funds till such time as all approvals are obtained. Developers face the dilemma of whether to make investments without PSAs and risk the entire investment or on the other hand, delaying investments till the PSA is signed or approved and risk being unable to complete the project in time, resulting in liquidated damages and under penalties under the PPA (fortunately regulatory commissions seem to be taking the view that project timelines will be extended in case of delays in procurement approvals, which is a welcome relief for developers).
Most importantly these delays undermines confidence in the robustness of the India’s tendering system for acquiring future renewable capacity, the vitality of which is the single largest factor that will attract long term institutional capital into Indian renewables, so that it can continue its blistering growth trajectory.
This article was originally published in Economic Times on 12 February 2021 Written by: Deepto Roy, Partner. Click here for original article
Read Less-
Disclaimer
This is intended for general information purposes only. The views and opinions expressed in this article are those of the author/authors and does not necessarily reflect the views of the firm.
The Bar Council of India does not permit solicitation of work and advertising by legal practitioners and advocates. By accessing the Shardul Amarchand Mangaldas & Co. website (our website), the user acknowledges that:
Click here for important public notice from the Firm.